Feb 23rd: Start of demo, say goodbye to awkward front door location/level, and super tiny and tall stairs to the loft. They've already leveled some of the unevenness in the floors in this picture.
March 27th: Removed window, put header in for new front door, and halfway thru knocking out the wall.
March 10th Exterior: New front porch roof finished (and missing corner of the roof filled in) and bricks cut to make way for the new front door.
March 10th Interior: new stairs built and entry way floor level raised
March 12th: front porch cement poured, and old front porch foundation raised a bit to faciliate closet that will be built there.
March 27th: Drywall and new front door installed.
(view from old front door)
April 6th: Walls painted and closet door on!
April 19th: Front entryway tile, hardwood and stair tops finished
June 8 and 9: Chris finishes up the stair railings by installing newel posts.
June 11th: Chris and I stain the front door and install a real lock/ handle and July 8th I finish painting the exterior trim.
first photo again for reference: